(1) Construction surveying and setting-out work shall commence concurrently with the establishment of temporary facilities upon site mobilization.
(2) Prior to construction, survey control points shall be verified and established jointly with the client and the supervising engineer. Operational procedures must be strictly followed during surveying to enhance precision and ensure quality.
(3) Given the scale of the project, dedicated personnel shall be assigned to handle construction surveying, ensuring the comprehensive and accurate provision of all survey data required during the construction phase.
(4) For horizontal layout during construction, a coordinate control system shall be established based on the coordinate points provided by the client and the positioning of reference lines; coordinate points and elevation control points shall be set up at appropriate locations along the river channel.
(5) Survey personnel shall assign unique identification numbers to survey markers and plot them on the general construction layout plan, noting relevant details, inter-marker distances, elevations, and angles to prevent errors; periodic inspections and verifications shall be conducted during construction to check for any displacement.
(6) Coordinate points and elevation control points shall be located on solid ground, away from construction interference, and in areas unlikely to be damaged or lost; concrete foundations and protective stakes shall be installed for these points.
(7) To ensure surveying accuracy, setting-out based on control points shall be followed by a re-verification survey prior to construction to guarantee the precision of the project.